Key Areas of Investigation
-
REFRIGERATION
AngloGold has a
scheduled maintenance plan requiring
refrigeration machines to be inspected
and heat balanced at regular intervals. A
typical finding is an insufficient heat
transfer across some of the condensers
and therefore efficiency losses. It is
possible to cost the effects of scale build-
up by a heat-balance and hence
determine the optimal time to clean this
equipment to minimise costs. AngloGold
have already established a pilot plant
testing the feasibility of automatic on line
efficiency monitoring and in-line tube
cleaning at their Great Noligwa mine. A
further potential saving is to insulate
these vessels.
-
COMPRESSORS
At AngloGold's
Kopanang and Tshepong mines, hot water
from compressor coolers is successfully
being used for supplying hostel change
houses with hot water requirements. The
same could be investigated for Elandsrand.
This is an effective use for waste heat.
Additionally the cost of losses caused by
the pressure drop across compressor
inlet air filters can be calculated. This will
give an indication of the best time to
change the filters.
-
COMPRESSOR COOLING TOWERS
There appeared to be room for some efficiency
improvement here. The cooling towers
were returning water above design
temperature to the compressor station.
This issue was taken up with mine staff.
-
ENERGY RECOVERY
Elandsrand mine recovers energy from water supplied to
the lower levels via pelton wheel turbine
driven generators. AngloGold is
similarly investigating alternative
energy saving methods of pumping
water, namely a three pipe chamber
feed system, operational at Tshepong,
and a water transformer being
installed at Moab Khotsong.
-
ENERGY MANAGEMENT
While energy is currently accounted to macro processes, as far as the metering allows,
the next level of accounting would be to
individual end users, for charging direct
utility costs. This is in line with current
AngloGold policy to distribute energy
costs as close as practicable to the end
user. Elandsrand appears to be on the
most cost effective tariff, currently using
the Eskom Real Time Pricing option on
tpo of their previous Nightsave KVA tariff.
Having highlighted the potential cost areas,
the team proceeded to evaluate and
categorise their benefit.
Evaluation Criteria
The following table identifies some of the key
areas where energy saving could be achieved.
These include: a cost estimate, the projected
benefit to the company (in monetary terms),
duration of the proposed project, the
estimated return on investment, as well as the
category of expenditure.
Type of expenditure was categorised as
follows:
-
IMPROVED HOUSEKEEPING (1)
Covered by maintenance budget.
-
LOW-COST MODIFICATION (2)
Covered by maintenance budget.
-
MEDIUM COST MODIFICATION (3)
A one-off investment, which is expensive in relation
to the value of existing equipment.
- HIGH COST MODIFICATION(4)
Substantial capital outlay on new
equipment.
| |
Costs |
Return |
Payback |
Category |
| Rigorous Compressed air saving programme |
R192 000 pa |
R384 000 pa |
6 months |
(1) |
| Rigorous inter-stage cooling maintenance/retrofit for surface air compressors |
R500 000 pa |
R1 200 000 pa |
5 months |
(2/3) |
| Rigorous after-stage cooling maintenance/retrofit for surface air compressors |
R500 000 |
See knock effects |
13 months |
(2/3) |
| Knock on effect on refrigiration from improving after-cooler performance |
|
R308 000 pa
(Value of additional heat input to mine) |
|
|
*All costs indicated above are 'high cost' estimates. In most cases actual costs will be lower.( Similar low savings estimates were chosen. )
Selected Results
After having completed the more detailed
analysis, new energy saving opportunities, as
well as those listed in the walk through, were
identified.
INVESTMENT VS ANTICIPATED PERIOD OF
PAYBACK
ALL MEASURES:
- The total investment required for the
execution of all the above listed projects
was R 1.293m.
- The total annual energy earning for the
above is: R1.99 m per annum
- The overall payback is approximately
eight months
MAINTENANCE & LOW COST MEASURES:
- The total investment required for the
execution of all the above listed
maintenance and low-cost (category (1)
& (2)) projects was R692 000
- The total annual energy earning for
this is: R1 584 000 pa
- The payback for these measures (class 1
& 2) is approximately five months
ENVIRONMENTAL CONSIDERATIONS:
- GLOBAL ENVIRONMENT:
Reduction in CO2 emissions:
9 700 000 tons pa
- NATIONAL ENVIRONMENT:
Reduction in SO2, emissions:
70 000 tons pa
Reduced environmental emissions from coalfired power stations providing less power.
Other Areas of Activity
ETA AWARDS:
- The Eta awards, sponsored by Eskom
and SABS, are awards to the year's most
outstanding energy efficiency initiatives.
The Energy monitoring and accounting
system used on AngloGold won this
award in 1997 by the developers - IST
Otokon.
- This year AngloGold is one of the finalists
for this year's award. Their entry involves
the implementation of a comprehensive
real time monitoring and control
scheme to respond to real time pricing
signals received daily from Eskom. The
investment was 0.33 million Rand and
the payback an impressive 7.2 million
rand per annum.
MONITORING AND TARGETING:
- AngloGold monitors and benchmarks the
energy performance of each operation.
Elandsrand has formed an energy
management team lead by the "utility"
engineer.
RETHINKING REFRIGERATION PRACTICES:
- The current utilities' engineer at
Elandsrand initiated the pre-cooling of
underground hot water dams directly.
This gives a better cooling thermal efficiency than conventional cooling from
the hot to the cold dam.
- Another initiative included decreasing
condenser water solids by changing the
existing configuration of the existing
plant, improving heat transfer and
therefore achieving higher efficiencies
and savings.
Recommendations
- PAYBACK OPPORTUNITY
By addressing the issues identified, the
exercise indicated that savings of R 2 million
per year, at a capital payback of less than a
year, are achievable.
-
COMPRESSED AIR GENERATION
The Elandsrand team has implemented several
excellent energy efficient initiatives. They are
currently improving surface compressor
control. Moore Controllers will optimise
compressor sequencing thus ensuring the
most efficient combination of operating the
five surface compressors.
-
COMPRESSOR INTER-STAGE COOLING
Ensuring that inter-stage and after-cooling for
the compressors run as close to design
conditions as practicably can make further
savings possible. A saving of about R100 000
a month could be derived from the decreases in
the input work to the compressor due to
correct isothermal operation. By ensuring
that compressed air is cooled before leaving
the compressors would contribute to
minimising the heat input to the mine. This
would have further spin off in improving
environmental conditions underground. In
some cases savings in capital equipment could
be achieved.
-
COMPRESSED AIR DISTRIBUTION
For compressed air distribution, it was
recommended that a rigorous leak detection
and repair program should be implemented
and that the responsible staff should have
more authority to enforce repair when this is
feasible. This finding has confirmed previous
work by AngloGold in this area. Some of the air
system may be rationalised by removing or
isolating dead legs and minimising pressure
drops, as well as isolating certain legs during
non-productive hours to prevent leakage. A
saving of about R 32000 per month can be
achieved by implementing an effective
campaign against leaks.
-
LIGHTING
AngloGold is investigating the potential for
upgrading lighting, and have produced a set of
performance criteria for lighting replacements.
Upgrading T12 fluorescent lighting systems to
T8 (including electronic ballasts) and
replacing incandescent lights with compact
fluorescent lighting (CFLs) should be
considered at Elandsrand. Group replacement of lights based on 70% of the lamp's
rated life should also be considered.
-
ENERGY MANAGEMENT TEAM
The commitment of the engineering staff to the
efficient use of energy on the mine was
evident. The possible savings in any plant are
directly proportional to the commitment of
those who apply these principles. Elandsrand
mine is to be commended in this regard.
-
CHARGING USERS FOR CONSUMPTION
AngloGold believes end-users should be held
accountable for energy efficiency. This should
assist in curtailing wastage.
-
REWARDING INITIATIVES AND PROVIDING INCENTIVES FOR STAFF
Energy efficiency often requires extra effort
from engineers , as it is not yet a high priority
issue in South Africa. Rewarding initiatives will
go some way in motivating staff to encourage
efficiency.
|
|