Key Areas of Investigation
-
ELECTRICAL ENERGY
An audit of all electrical consumption from each
substation was completed to obtain a clearer picture of electricity consumption. It was found that the power factor
could be improved.
-
BOILERS AND STEAM SYSTEM
A comprehensive investigation touched on
these aspects: steam flow rate equipment: continuous boiler control; flash
steam-, wort kettle vapour-, and
condensate recovery from the brew
house: use of steam accumulator; and
condensate recovery from the packaging
hall.
-
COMPRESSED AIR
This is an expensive form of energy and it was important to
determine the efficiency and application.
-
REFRIGERATION
Streamlining the energy usage would include rescheduling of refrigeration loads, compressor
sequencing and control, as well as cooling towers.
-
AIR CONDITIONING
It was noticed that small single units, which are not efficient
in energy use, are used rather than
efficient centralised units.
- ENERGY MANAGEMENT
It appeared that the timing of production schedules was
made arbitrarily. With little or no effect on
the final product, these schedules could
be changed to make a significant
reduction in utility consumption and
eventually costs.
Having highlighted the potential saving in
energy costs, the team proceeded to evaluate
these key issues according to succinct
evaluation criteria.
Evaluation Criteria
The following table identifies some of the key
areas where energy saving could be achieved
resulting from this work and selected examples
of other SAB initiatives. Where possible, these
include: a cost estimate (which was a 'high-end
cost' where a range was considered), the
projected benefit to the company (in money
terms), duration of the proposed project (time
frames), the estimated return on investment
(months) as well as the category of action
required.
Proposed action for the case studies evaluated
in this program were categorised as follows:
-
IMPROVED HOUSEKEEPING (1)
Covered by maintenance budget or
required changes in behaviour and/or
schedules
-
LOW-COST MODIFICATION (2)
-
RETROFIT (3)
Refers to a significant one-off invest
ment which is expensive in relation to the
value of existing equipment
-
SUBSTANTIAL CHANGE INVOLVING
SIGNIFICANT INVESTMENT (4)
Similar to retrofit, costs may be substantial and it usually requires capital
outlay on new equipment
| |
Costs |
Return |
Payback |
Category |
| Improved power factor correction |
R60 000 |
R120 000 pa |
6 months |
(3) |
| Refrigiration load management |
R650 000 |
R650 000 pa |
1 year |
(1 & 4) |
Spent grain removal Load management |
Zero |
R6 000 pa |
Immediate |
(1) |
Rigorous program for Saving compressed air |
R75 000 |
R150 000 pa |
6 months |
(1) |
Rigorous program for Saving steam |
R100 000 |
R200 000 pa |
6 months |
(1) |
| Boiler automation |
R100 000 |
R132 000 pa |
9 months |
(3) |
| Use of waste biogas |
R32 000 |
R52 000 pa |
9 months |
(2) |
| Efficient lighting upgrades |
R165 000 |
R165 000 pa |
1 year |
(3) |
*All costs indicated above are 'high cost' estimates. In most cases actual costs will be lower.There are of course many more.
Selected Results
After having completed the more detailed
analysis, new energy saving opportunities, as
well as those listed in the walk through, were
identified. The table below highlights some of
the main recommendations from this work, and
some other key SAB energy and money saving
programs.
Other Areas of Activity
- Electrode Boilers (CT) SAB in Newlands, Cape Town, have recently switched from using coal
and oil fired boilers to electrode boilers. This change has resulted in a boiler efficiency
improvement of close to 15%, and the reduction of thousands of tons of local pollutants,
a sensitive and scenic area.(4)
- Monitoring and targeting SAB has a national monitoring targeting program fostering
competition and comparison between plants.(1)
| |
Costs |
Return |
Payback |
Category |
| Improved power factor correction |
R60 000 |
R120 000 pa |
6 months |
(3) |
| Refrigiration load management |
R650 000 |
R650 000 pa |
1 year |
(1 & 4) |
Spent grain removal Load management |
Zero |
R6 000 pa |
Immediate |
(1) |
Rigorous program for Saving compressed air |
R75 000 |
R150 000 pa |
6 months |
(1) |
Rigorous program for Saving steam |
R100 000 |
R200 000 pa |
6 months |
(1) |
| Boiler automation |
R100 000 |
R132 000 pa |
9 months |
(3) |
| Use of waste biogas |
R32 000 |
R52 000 pa |
9 months |
(2) |
| Efficient lighting upgrades |
R165 000 |
R165 000 pa |
1 year |
(3) |
Recommendations
- POWER FACTOR CORRECTION
Existing power factor correction equipment
could be upgraded to a power factor of greater
than 0.97 to achieve a saving of approximately
R120 000 per annum.
-
COMPRESSORS
Suggestions included: a riqorous leak
detection and repair program, shifting
compressed air loads (such as for the removal
of spent grains) and investigating the most
efficient compressor loading.
-
REFRIGERATION
The SAB plant at Prospecton had moved some
of the load to off peak tariff times at night and
this practice should be continued. Additionally,
it may be possible to produce some, or all of the
chilled liquor at night, and to store it for daytime use. Large quantities could be partially
cooled or small quantities could be completely
cooled. This would require a short optimisation exercise to determine the best practice
with a projected desired payback.
-
BOILER PLANT OPERATION AND STEAM USAGE
Installing an in-situ oxygen probe at the ID fan
outlet for real-time monitoring would help
optimise combustion air to fuel ratios. A digital
gauge for stoker speed measurement should
be used and all measuring equipment calibrated.
A further energy saving is possible using
biogas. Biogas produced in the purification
plant could be piped to the boiler plant and
introduced directly to the combustion chamber
at the forced draft fan inlet. This should be
viewed as an interim measure due to its short
payback. The process could result in quicker
(more energy and cost efficient) start-ups and,
due to the large storage of biogas, help meet
'spikes' in steam demand. Approximately one
km of HDPP pipe feeding the gas to the boilers,
with the right pressure regulation, would act as
a 'gas storage vessel'.
There is scope for a rigorous steam leak and
trap repair program. This is ongoing at SAB
and could be further encouraged via an energy
management team.
ENERGY MANAGEMENT TEAM
TO ACHIEVE THE DESIRED RESULTS, THESE
KEY ISSUES HAD TO BE ADDRESSED
-
ENERGY MONITORING AND TARGETING
(M&T). Prospecton currently has a well
run utilities department and the minor
adjustments required would not pose
any difficulty. SAB has a national energy
monitoring scheme, which allows
different plants to 'compete' and be
compared. Generic suggestions, for M &
T as well as the topics that follow, are
outlined in more detail in the 'How to'
booklet of the 3E program.
-
RESPONSIBILITY AND ACCOUNTABILITY
(The following is a common theme in
plants audited.) Due to the desegregated nature of 'utilities' consumption,
not one particular division assumes
responsibility for planning and cost
effective utilisation. Significant savings
can be achieved by introducing basic
constraints to these various consuming
sectors. These should be cost driven
with final accountability resting with the
accounts department and management.
Incorporating a summary to an existing
regular report could facilitate this. This
would also provide a forum for recommendations and innovation.
-
CHARGING USERS FOR CONSUMPTION
This is recommended to improve
maintenance and curtail wastage.
-
REWARDING INITIATIVES AND PROVIDING INCENTIVES FOR STAFF
'Energy efficiency' often requires engineers
'go the extra mile', as it is not yet
accepted practice in South Africa. This
might be adjusted by rewarding
initiatives and creating incentives
to motivate staff.
Bottom Line
INVESTMENT VS ANTICIPATED PERIOD OF PAYBACK
ALL MEASURES:
- The total investment required for the
execution of all the above listed projects
was R 1.18 million.
- The total annual energy earning for the
above is: R1.37 million per annum
- This represents a saving of 8% of the
total energy consumption
- The overall payback is approximately ten
months
MAINTENENCE & LOW COST MEASURES:
-
The total investment required for the
execution of all the above listed
maintenance and low-cost (category (1)
& ((2))projects was R175 000
- The total annual energy earning for this
is: R258 000 pa
- The payback for these measures (class 1 & 2) was about six months
ENVIRONMENTAL CONSIDERATIONS
-
The adoption of all of the efficiency
measures will result in a saving of 1 600
tons of coal pa with an associated
reduction in emissions.
|
|