Key Areas of Investigation
-
ELECTRICAL ENERGY
An audit of all electrical consumption from each
substation was completed to obtain a
clearer picture of electricity
consumption. It was found that the
power factor could be improved.
-
BOILERS AND STEAM SYSTEM
A comprehensive investigation
touched on steam flow rate equipment and continuous boiler control.
-
COMPRESSED AIR
This is normally a very expensive form of energy and it
was important to investigate its
efficiency and application.
-
ENERGY MANAGEMENT
It appeared that the timing of production
schedules was made almost arbitrarily. With little or no effect on
the final product, these schedules
could be amended to reduce utility
consumption, and eventually costs.
Having highlighted the potential saving in
energy costs, the team proceeded to evaluate
these key issues according to succinct
evaluation criteria.
Evaluation Criteria
The following table identifies some of the key
areas where energy saving could be achieved
resulting from this work and selected examples
of other SAPPI initiatives. Where possible,
these include: a cost estimate (which was a
'high-end cost' where a range was considered), the projected benefit to the company (in
money terms), the estimated return on
investment (months) as well as category of
action required. Results were reviewed by the
Mandini engineering staff.
Proposed action for the case studies evaluated
in this program were categorised as follows:
-
IMPROVED HOUSEKEEPING(1)
Covered by maintenance budget or
required changes in behaviour
and/or schedules
-
LOW-COST MODIFICATION (2)
-
o RETROFIT (3)
Refers to a significant one-off
investment which is expensive in
relation to the value of existing
equipment.
-
SUBSTANTIAL CHANGE INVOLVING
SIGNIFICANT INVESTMENT (4)
Substantial capital outlay on new equipment.
| |
Costs |
Return |
Payback |
Category |
| Improved power factor correction |
R270 000 |
R540 000 pa |
6 months |
(3) |
| Rigorous program for saving compressed air |
R53 000 |
R106 000 pa |
6 months |
(1) |
Rigorous program for Saving steam |
R2 011 000 |
R4 020 000 pa |
6 months |
(1) |
| Efficient lighting upgrades |
R888 000 |
R888 000 pa |
1 year |
(3) |
*All costs indicated above are 'high cost' estimates. In most cases actual costs will be lower.There are of course many more.
Selected Results
After having completed the more detailed
analysis, new energy saving opportunities, as
well as those listed in the walk through, were
identified. The table below highlights some of
the main recommendations from this work, and
some other key SAPPI Mandini energy and money saving
programs.
Other Areas of Activity
- STEAM OPTIMAISATION: SAPPI has an ongoing drive to rationalise the Mandini
plants use of steam and formulate a co-ordinated approach to steam
monitoring and targeting. This also included a recent extensive steam trap audit.(1)
- 'OPERATION CLINKER' is a program that has been started to try and identify the
major energy losses in the Mandini plant and quantify potential energy losses.(1)
| |
Costs |
Return |
Payback |
Category |
| Improved power factor correction |
R270 000 |
R540 000 pa |
6 months |
(3) |
| Rigorous program for saving compressed air |
R53 000 |
R106 000 pa |
6 months |
(1) |
Rigorous program for Saving steam |
R2 011 000 |
R4 020 000 pa |
6 months |
(1) |
| Efficient lighting upgrades |
R888 000 |
R888 000 pa |
1 year |
(3) |
Recommendations
- POWER FACTOR CORRECTION
Improving the overall power factor for the plant
potentially holds these benefits for SAPPI:
- increase of plant capacity
- reduction of electrical maximum demand charge
- fewer power losses in feeders,
transformers and distribution equipment
The table illustrates the potential saving of
R540 000 if the power factor is improved to
0,98. A more detailed quote for an upgraded
power factor correction system should be
obtained in order to determine the payback
period for this option.
-
COMPRESSORS
Compressed air leakage was identified as a
problem area. A leakage prevention plan could
reduce leakage from approximately 25% to 8%
and this would result in an estimated saving of
R106 000 per annum. An audit of the compressed
air system is recommended.
In addition to the leakage problem, it was noted
that the compressed air was used to regulate
ambient temperatures during the summer and
for general cleaning purposes. Training and
education about energy issues could help
eliminate such practices.
-
BOILER PLANT OPERATION
The boiler report contained these recommendations:
- the gas and air tightness of boilers
should be checked regularly (air-
heater and casing leaks).
- care should be exercised when
operating above maximum continuous rating (MCR) as this could reduce
the life span of the boiler
- the feed water and steam flow meters
should be calibrated to determine
boiler leaks.
-
LIGHTING
The suggested amendments in lighting as
contained in the table will result in an approximate saving of up to 25% (T12 to T8) and up to
70% (CFLs instead of incandescent lights).
Group replacement of lights based on 70% of
the lamp's rated life will facilitate 25% savings
due to the reduced maintenance labour cost.
ENERGY MANAGEMENT TEAM
TO ACHIEVE THE DESIRED RESULTS, THESE
KEY ISSUES HAVE TO BE ADDRESSED:
-
ENERGY MONITORING AND TARGETING
(M&T). SAPPI Mandini currently has a well-
run utilities department, and the minor
adjustments required already form part of the
planning for next year. (Generic suggestions,
for M & T as well as the topics that follow, are
outlined in more detail in the 'How to' booklet
of the 3E program.) Monitoring and targeting
should arguably receive the most attention as
it is a most significant issue due to the size of
the installation and the 'organic growth' type
of expansion of the plant. It is reccomended
that, where possible, 'real-time' monitoring
should take place.
-
RESPONSIBILITY AND ACCOUNTABILITY
(The following is a common theme in plants
audited.) Due to the desegregated nature of
'utilities', not one particular division assumes
responsibility for planning and cost effective
utilisation. Significant savings can be achieved
by introducing basic constraints to these
various consuming sectors. These should be
cost driven with final accountability resting with
the accounts department and management.
Incorporating a summary to an existing
regular report could facilitate this. This would
also provide a forum for recommendations and
innovation.
-
CHARGING USERS FOR CONSUMPTION
This is recommended to improve maintenance and
curtail wastage. SAPPI Mandini had, prior to
the completion of this energy audit, planned to
implement this measure more stringently.
Such a step will force users to manage their
energy consumption tightly and result in
energy efficiency measures being driven from
the bottom up. This bottom up approach
commonly results in energy savings of 10% -
20%.
-
REWARDING INITIATIVES AND PROVIDING INCENTIVES FOR STAFF
'Energy efficiency' often requires engineers to 'go the extra mile', as it
is not yet accepted practice in South Africa.
This may be enhanced by rewarding initiatives
and creating incentives to motivate staff.
Bottom Line
INVESTMENT VS ANTICIPATED PERIOD OF PAYBACK
ALL MEASURES:
- The total investment required for the
execution of all the above listed
projects is R3.22m.
- The total annual energy earning for
the above is R5.55 m. (Following
implementation, an amount of
approximately R200 000 per annum
should be included in budgets of
future years to facilitate and motivate
the required activities.)
- This represents a saving of more
than 5% of the total energy consumption.
- The overall payback is approximately
seven months.
MAINTENENCE & LOW COST MEASURES:
-
The total investment required for the
execution of all the above listed
maintenance and low cost projects is
R2.06m.
- The total annual energy earning for
this is R4.13m.
- The payback for these measures
(class 1 & 2) is about six months.
ENVIRONMENTAL CONSIDERATIONS
-
NATIONAL ENVIRONMENT
Reduction in CO2,emissions: 65 200 tons per annum.
-
LOCAL ENVIRONMENT
Reduction in SO2
emissions: 1185 tons per annum.
|
|